Audit Finds Months-Long Delays, Millions in Cost Overruns In Park Construction Projects
City Comptroller John C. Liu today announced that the Parks
Department’s failure to monitor its capital
construction projects had allowed almost half of those projects to
finish late and 10% to go significantly over budget in Fiscal Years 2010
and 2011.
“New
Yorkers and visitors alike love our parks. Repairs and upgrades must
be better managed not only to reduce wasteful spending, but also
to minimize the duration of park closures,” Comptroller Liu said. “The
Parks Department can do better.”
In
FY2010-FY2011, the Parks Department completed 315 capital construction
projects, at a cost of $496.3 million. Comptroller Liu’s audit
found that:
·
149
(47%) of those projects finished late. The projects were 218 days late
on average. These late projects were supposed to have been complete
within 284 days on average,
so the delays resulted in almost doubling the length of time planned
for completion.
·
30
projects combined to rack up $10 million in cost overruns, over and
above the additional $8.6 million in contingency allowances for overruns
that they burned through.
The projects had been budgeted at a combined cost of $69.6 million.
·
Despite
spending $4 million to correct consultants’ design errors and omissions
on various projects, the Parks Department did not use its right to try
and recoup the
money.
Comptroller
Liu’s Audit Bureau launched the audit in response to numerous
complaints from New Yorkers, including calls to the Comptroller’s
212-NO-WASTE hotline, and after independently assessing
that an examination of the agency’s capital projects was warranted.
The
audit recommended several steps that the Parks Department should take
to better ensure that projects are completed on time and within budget.
For example, the audit recommended that
the Parks Department flag projects for priority completion so that
delayed work can be expedited.
Today’s audit is available for download here:
http://www.comptroller.nyc. gov/bureaus/audit/yearlyview. asp?selaudyear=2013
The complete list of projects that were delayed or overbudget is available in the audit’s appendix.
Parks Projects That Were Significantly Overbudget And Delayed
POE PARK VISITORS CENTER
|
Bronx
|
SOUNDVIEW PARK - CONSTR OF
|
Bronx
|
EDENWALD PLAYGROUND
|
Bronx
|
CHARLTON GARDEN PLGD
|
Bronx
|
SCHOOLYARDS @ PS105K, PS 112, PS 205, PS 247
|
Brooklyn
|
KAISER PARK - REC BLDG
|
Brooklyn
|
ROBERT E. VENABLE PARK
|
Brooklyn
|
ROBERT E. VENABLE PARK
|
Brooklyn
|
RIVERSIDE PARK
|
Manhattan
|
PAVEMENTS, SIDEWALKS
|
Manhattan
|
UNION SQUARE PK - CONSTR OF
|
Manhattan
|
SCHOOLYARDS @ PS 129Q, PS 79, JHS 25, PS 159
|
Queens
|
SCHOOLYARDS @ PS 116Q & IS 238
|
Queens
|
CONSTR OF TUSCAN GARDEN & LEMON HOUSE, SNUG HARBOR
|
Staten Island
|
Visit www.comptroller.nyc.gov for
the latest news, events, and initiatives.
Follow Comptroller Liu on Twitter, YouTube.
Follow Comptroller Liu on Twitter, YouTube.
No comments:
Post a Comment