Governor Hochul Announces Award of $182 Million Utility Relocation Contract for Second Avenue Subway Phase 2 Project

Rendering of the Second Ave Subway after phase 2 of construction shows a busy corner with an above ground overpass  

New York City Based Company Chosen to Start Relocating Complex Underground Utility Infrastructure

SAS Phase 2 Project Will Bring Transit Equity to East Harlem

Governor Kathy Hochul today announced that the Metropolitan Transportation Authority has awarded the first construction contract for the extension of the Second Avenue Subway from 96 Street to 125 Street in Harlem to C.A.C. Industries, Inc. a family-owned heavy civil contractor based in New York City, specializing in infrastructure projects. The initial $182 million award is for the first component of the Second Avenue Subway Phase 2 project, which will finally deliver subway service to residents of East Harlem, one of the most transit-dependent neighborhoods in New York City.

“We're moving full speed ahead to extend the Second Avenue Subway to East Harlem, expanding transit access for thousands of New Yorkers," Governor Hochul said. “This critical milestone will put shovels in the ground for the next phase of this transformative project. East Harlem has dreamed of transit access for decades -- and we're committed to getting the job done.”

This is the first of four construction contracts for the new line, which will extend the Q train from 96 Street to 125 Street, serving more than 100,000 average daily riders and building three new ADA-accessible stations for the East Harlem community. The contract will relocate underground utilities from 105 Street to 110 Street on Second Avenue at the site of the future 106 Street Station, in order to facilitate the subsequent cut-and-cover construction of the station.

New York City has some of the most complex underground utilities networks in the world – much of which is unmapped – which can add delays and costs once projects are underway. Advancing utility relocation ahead of station and tunnel construction is a major lesson learned from Phase 1 of Second Avenue Subway, which will help to reduce unnecessary costs and delays on Phase 2 of the project.In July, the MTA also unveiled new conceptual renderings of the proposed stations for the extension, providing future riders with a first-ever glimpse into the potential station interior and exterior designs. The draft renderings are subject to further design development and are available here.

Revenue from congestion pricing will support $15 billion in funding for critical projects in the MTA's current capital program, which includes Second Avenue Subway Phase 2.

As part of the MTA's commitment to delivering key infrastructure projects better, faster, and cheaper, the first contract for Phase 2 incorporates lessons learned from Second Avenue Subway Phase 1. Addressing utility relocation requirements upfront will reduce the risk of unexpected costs or delays later as construction progresses. The first contract will also include temporary streetscape modifications that will be required during construction, including new bike lanes to replace those that will be impacted by construction on Second Avenue, and building remediation in preparation for future contracts for the new subway station at 106 Street.

Additional cost containment initiatives in Phase 2 include reuse of a tunnel segment that was built in the 1970s from 110 Street to 120 Street along Second Avenue, early real estate acquisition, adoption of best value contract structures like A+B contracts, reduction in back-of-house and ancillary space, and close coordination of contracts.

About Phase 2

The second phase of the project will extend Q train service from 96 Street north to 125 Street and then west on 125 Street to Park Avenue, approximately 1.5 miles in total. There will be two new stations at 106 Street and 116 Street on Second Ave, and a direct passenger connection with the existing 125 Street subway station on the Lexington Avenue subway line. Phase 2 will also feature an entrance at Park Avenue to allow convenient transfers to the Metro-North Railroad 125 Street Station.

Each station will have above-ground ancillary buildings that house ventilation, mechanical, and electrical equipment, as well as space for possible ground-floor retail and community uses. The expansion will serve an additional 100,000 daily riders and provide three new ADA accessible stations -- raising the bar for customer comfort and convenience. Increased multimodal transit connectivity at the 125 Street station at Park Avenue with connections to the 4 5 6, Metro-North trains and the M60 Select Bus Service to LaGuardia Airport, will allow for convenient transfers to other subway and commuter rail lines, facilitating smoother, faster transportation across the city and metropolitan region.

About Phase 1

Phase 1 of the project extended the Q line from 63 Street to 96 Street and was New York City's largest expansion of the subway system in 50 years. Service opened on January 1, 2017, with additional stations at 72 Street and 86 Street. Since its completion, the Second Avenue Subway has carried more than 130 million passengers in total, including more than 200,000 passengers on a typical pre-pandemic day.